DUE DILIGENCE
Prior to beginning design, our team conducted a thorough due diligence process to identify critical paths and other aspects that would affect the proposed design.
TECHNICAL ANALYSIS
Our team completed a series of technical analysis including:
​
Survey
Geotechnical Report
Environmental Impact Report
Traffic Study
CRITICAL PATHS
Our team identified various critical paths on site including:
​
Active & Abandoned Railroads
Hazardous Pipeline
Existing Trunk Sewer and Sewer Line
Existing Onsite Channel
RESEARCH
Our team researched applicable standards for the development including those from City of Pomona and Los Angeles County​.
​
In an effort to implement best practices throughout our design process​, we also consulted with various CPP CE/CEM faculty, land development companies, and local jurisdictions including City of Pomona and City of San Dimas.